HomeMy WebLinkAboutItem 07Feasibility Report
Prepared for:
701 Xenia Avenue South, Suite 300 Minneapolis, MN 55416 763.541.4800
FEASIBILITY REPORT
2011STREETIMPROVEMENT PROJECT
FOR THE
CITY OF LAKEVILLE, MINNESOTA
December 16, 2010
Prepared By:
WSB & Associates, Inc.
701 Xenia Avenue South, Suite 300
Minneapolis, MN 55416
763-541-4800
763-541-1700 (Fax)
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
December 16, 2010
Honorable Mayor and City Council
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044
Re:Feasibility Report
2011Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Dear Honorable Mayor and City Council:
Transmitted herewith for your review is a feasibility report which addresses improvements
associated with the 2011 Street Improvement Project.
We are available at your convenience to discuss this report. Please do not hesitate to contact me
at 763-287-7173 if you have any questions regarding this report.
Sincerely,
WSB & Associates, Inc.
Morgan A. Dawley, PE
Project Manager
Enclosure
srb
CERTIFICATION
I hereby certify that this plan, specification, or report was prepared
by me or under my direct supervision and that I am a duly
Licensed Professional Engineer under the laws of the State of
Minnesota.
Monica R. Heil, PE
Date: December 16, 2010Lic. No. 47497
Quality Control Review Completed By:
Morgan A. Dawley, PE
Date: December 16, 2010Lic. No. 44178
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
TABLE OF CONTENTS
TITLE SHEET
LETTER OF TRANSMITTAL
CERTIFICATION SHEET
TABLE OF CONTENTS
1.EXECUTIVE SUMMARY...............................................................................................1
2.STREET AND UTILITY IMPROVEMENT PROJECT..............................................2
2.1Introduction..............................................................................................................2
2.1.1Authorization...............................................................................................2
2.1.2Scope............................................................................................................2
2.1.3Data Available.............................................................................................2
2.2General Background................................................................................................2
2.2.1Project Location...........................................................................................2
2.3Existing Conditions..................................................................................................3
2.3.1Surface.........................................................................................................3
2.3.2Storm Sewer.................................................................................................4
2.3.3Wetlands......................................................................................................5
2.4Proposed Improvements...........................................................................................6
2.4.1Surface.........................................................................................................6
2.4.2Storm Sewer.................................................................................................6
2.4.3Water and Sanitary Sewer Improvements....................................................8
2.4.4Street Sign Replacement..............................................................................8
2.4.5Mailbox Replacement..................................................................................8
2.4.6Permits/Approvals........................................................................................8
2.4.7Construction Access.....................................................................................9
2.4.8Public Involvement......................................................................................9
2.5Future Improvements and Additional Considerations.............................................9
2.5.1Street Lighting within the Glenn Addition..................................................9
3.FINANCING....................................................................................................................10
3.1Opinion of Cost......................................................................................................10
3.2Funding..................................................................................................................10
4.PROJECT SCHEDULE..................................................................................................12
5.FEASIBILITY AND RECOMMENDATION..............................................................13
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
TABLE OF CONTENTS (continued)
Appendix A
Figure 1:Location Map
Figure 2:Typical Section –Local Streets
th
Figure 3:Proposed Street and Storm Sewer Improvements –205Street, Idalia Avenue,
thth
Iceland Avenue, 207Street, 207Court
Figure 4:Proposed Street and Storm Sewer Improvements –Iberia Avenue,
th
205Street, Hughes Avenue, Howland Avenue, Hunter Court
th
Figure 5:Proposed Street and Storm Sewer Improvements –Upper 206Street, Lower
thth
208Street, 208Street
Appendix B
2011 Street Improvement Project Opinion of Probable Cost
Appendix C
Assessment Map ID
Assessment Roll
Appendix D
2010 Geotechnical Report –Soil Boring Logs
Appendix E
Neighborhood Informational Meeting Minutes –October 28, 2010
Public Comment Summary
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
1.EXECUTIVE SUMMARY
The 2011 Street and Utility ImprovementProject includes surface and utility improvements to
the following roadways totaling approximately 13,710 feet (2.60 miles):
th
205Street (Dodd Boulevard to east terminus at Progressive Railway right of way)
th
Idalia Avenue (north terminus to 207Street)
thth
Iceland Avenue (205Street to 207Street)
th
207Street (Dodd Boulevard to Progressive Railway right of way)
thth
207Court (207Street to cul-de-sac)
th
Iberia Avenue (Kenwood Trail to 205Street)
th
205Street (Iberia Avenue to Holyoke Avenue)
th
Hughes Avenue (205Street to cul-de-sac)
th
Howland Avenue (205Street to cul-de-sac)
Hunter Court (Kenwood Trail to cul-de-sac)
thth
Upper 206Street (east of 8510 Upper 206Street to 20678 Hershey Avenue)
thth
Lower 208Street (Holiday Avenue to 208Street)
thth
208Street (Lower 208Street east to cul-de-sac)
The deteriorated condition of the existing roadway surfaces and the drainage issues experienced
along these streets make the proposed improvements necessary. Reclamation of the existing
bituminous pavementand roadway reconstruction is recommended for all streets within the
project area. New concrete curb and gutter is proposed to be installed along all roadways within
the Glenn Addition where only bituminous curb currently exists. Structurally deficient concrete
curb and gutter will be replaced elsewhere within the project limits. Proposed utility
improvements include the installation of new storm sewer facilities and the reconstruction of
structurally deficient sanitary sewer manholes.
$2,820,000
The total estimated project cost for the 2011 Street Improvement Project is which
includes a 10%contingency and 28% indirect costs for legal, engineering, administrative, and
financing costs. The project is proposed to be funded through special assessments to benefitting
property owners and City funds.
The project is proposed to be completed in 2011, including all restoration items. The project is
feasible, necessary, and cost effective from an engineering standpoint and should be constructed
as proposed herein.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 1
2.STREETAND UTILITY IMPROVEMENT PROJECT
2.1Introduction
2.1.1Authorization
On December 6, 2010, the Lakeville City Council authorized the preparation of an
engineering feasibility report for the 2011 Street Improvement Project.
2.1.2Scope
The 2011 Street Improvement Project includes surface and drainage improvements for
areas identified by the City’s Pavement Management Program for reconstruction.
2.1.3Data Available
Information and materials used in the preparation of this report include the following:
City of Lakeville Record Plans
Dakota County Topography Maps
Utility Record Drawings
Lakeville Water Resources Management Plan, Barr Engineering, dated June 2008
Certified Grading Plans and the Stormwater Calculations for Regional
Stormwater Basin SC-41-1, Constructed with the Marion Fields Development
Field Observations of the Area and Discussions with City Staff
Field Survey
Televising Reports for the Sanitary Sewer System (Completed by the City of
Lakeville)
Water Main Leak Survey (Completed by the City of Lakeville)
Geotechnical Evaluation Report, Braun Intertec, dated December 2010
City of Lakeville Street Reconstruction Assessment Policy
FEMA Floodplain Maps, dated 1998
2.2General Background
2.2.1Project Location
The streets proposed for improvements include:
th
205Street (Dodd Boulevard toeast terminus at Progressive Railway right of
way)
th
Idalia Avenue (north terminus to 207Street)
thth
Iceland Avenue (205Street to 207Street)
th
207Street (Dodd Boulevard to Progressive Railway right of way)
thth
207Court (207Street to cul-de-sac)
th
Iberia Avenue (Kenwood Trail to 205Street)
th
205Street (Iberia Avenue to Holyoke Avenue)
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 2
th
Hughes Avenue (205Street to cul-de-sac)
th
Howland Avenue (205Street to cul-de-sac)
Hunter Court (Kenwood Trail to cul-de-sac)
thth
Upper 206Street (east of 8510 Upper 206Street to 20678 Hershey Avenue)
thth
Lower 208Street (Holiday Avenue to 208Street)
thth
208Street (Lower 208Street east to cul-de-sac)
Figure 1Appendix A
The project areas are shown in of of this report.
2.3Existing Conditions
2.3.1Surface
Streets within the proposed improvement area are aging and experiencing various
severities of alligator cracking, block cracking, transverse cracking, longitudinal cracking
and localized drainage issues. All project areas contain landscaping, trees, and numerous
other private improvements beyond the edge of the roadway and within City right of way.
th
The 5-foot-wide concrete sidewalk located along the south side of Upper 206Street is
the only existing pedestrian facility located within the project area.
Table 1
below provides a summary of existing street conditions within the 2011 Street
Improvement Project.
Table 1 –2011 Street Improvement Project
Summary of Existing Street Conditions
Approx.
Year of
Street Curb Sub-base Avg. Bit. Original
Street NameROWWidthType(aggregate)Sub-gradeSectionConstruction
3’ Poorly
th
205Street (west of 2.5" -
60’32’ B-BBit.8-10”Graded 1971
Progressive Rail ROW)5.5”
Sandy Fill
5’ Poorly
Idalia Avenue60’32’ B-BBit.9”Graded 2”1971
Sandy Fill
16’ Poorly
Iceland Avenue60’32’ B-BBit.8”2.5”1971
Graded Sand
4’ –5’
Poorly 4.5” -
th
207Street60’32’ B-BBit.7-9.5”1971
Graded 6.5”
Sandy Fill
4’ Clayey
th
207Court50’32’ B-BD4129”2.5”1974
Sand Fill
4’ –6’
Poorly
Iberia Avenue60’32’ B-BB6184” –6.5”3” -6”1972
Graded
Sandy Fill
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 3
Table 1 –2011 Street Improvement Project
Summary of Existing Street Conditions
Approx.
Year of
Street Curb Sub-base Avg. Bit.
Original
Street NameROWWidthType(aggregate)Sub-gradeSectionConstruction
4’ Poorly
th
205Street (east of
Graded 3”1961
60’32’ B-BB6184” –5”
Progressive Rail ROW)
Sandy Fill
6’ Poorly
Hughes Avenue60’32’ B-BB6126”2”1971
Graded Sand
6’ Poorly
Howland Avenue60’32’ B-BB6185”Graded 3”1972
Sandy Fill
6’ Poorly
Hunter Court60’32’ B-BD4124.5”Graded 2.5”1984
Sandy Fill
4’ Poorly
th
Upper 206Street60’36’ F-FB6185”Graded 2”1984
Sandy Fill
6’ Poorly
th
Lower 208Street60’32’ B-BB6184” –8”2” -3”1968
Graded Sand
B618 2’Poorly
th
208Street60’32’ B-Band 8”Graded 3.25”1972
D412Sandy Fill
A copy of the geotechnical soil boring logs prepared for this project by Braun Intertec in
Appendix D
December 2010 may be found in of this report.
2.3.2Storm Sewer
ththth
Glenn Addition: 205Street, Idalia Avenue, Iceland Avenue, 207Street and 207Court
The existing storm sewer system providing drainage for the entire Glenn Addition
consists of the following:
th
Three catch basins located at the intersection of Iceland Avenue and 207Street
thth
Two catch basins located along 207Street between Iceland Avenue and 207
Court
thth
Two catch basins located along 207Court at 207Street
City as-built information indicates runoff collected by these catch basins travels through
existing storm sewer pipe and outlets into Regional Stormwater Basin SC-41-1, which
th
was constructed with the Marion Fields development (the basin is located south of 207
Street, west of and adjacent to the Progressive Rail right of way). As-built and survey
data indicate the existing storm sewer pipe leadingto this storm water basin is located
within the Progressive Rail right of way.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 4
Historically, the existing storm sewer facilities within the Glenn Addition have proven
inadequate. A lack of concrete curb and gutter, minimal street grades and an inadequate
number of inlet structures within the Glenn Addition has resulted in significant drainage
issues. Poorly draining areas within the development are easily visible and have
contributed to the deterioration of the pavement within the Glenn Addition.
th
Iberia Avenue, 205Street, Hughes Avenue, Howland Avenue and Hunter Court
The existing storm sewer system in this area of the project consists of the following:
th
Minimal storm sewer along Iberia Avenue and 205Street.
A culvert located along the shared lotline for 20365 and 20370 Hughes Avenue.
This culvert provides drainage for most of Hughes Avenue and is connected to a
storm sewer manhole constructed within the drainage and utility easement
adjacent to the Lake Vale townhome development.
Two curb cuts within the Howland Avenue cul-de-sac are designed to drain runoff
from Howland Avenue. This runoff is intended to flow overland through James
Jensen Park to the existing drainage channel referred to as the North Branch of
South Creek. However, insufficient grade through James Jenson Park results in
much of the runoff collecting in the cul-de-sac curb line of Howland Avenue until
such time as it evaporates or infiltrates.
A single catch basin located within the cul-de-sac of Hunter Court drains the
entire street. Historically, this single inlet has proved an adequate means of
stormwater drainage.
ththth
Upper 206Street, Lower 208Street, 208Street
The existing storm sewer system in this area of the project consists of the following:
th
Six existing catch basins along Upper 206Street
th
Two catch basins at the low point of Lower 208Street
th
Two catch basins at the low point of the 208Street cul-de-sac, east of the
th
intersection with Lower 208Street.
th
Historically, the existing storm sewer facilitiesalong Upper 206Street have proven
adequate. However, more than 24 acres currently drain to the two catch basins located at
th
the low point along Lower 208Street. The property owners located at 8330 and 8340
th
Lower 208Street, adjacent to the low point in the road, experience water entering their
garages and low floors when storm water overtops the existing curb line during large
storm events.
2.3.3Wetlands
No wetlands exist within the project.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 5
2.4Proposed Improvements
2.4.1Surface
Roadway reconstruction is proposed for each of the streets within the project due to the
level of distress the bituminous pavement in the area is experiencing, and will consist of
the complete removal of the existing bituminous roadway. New barrier-style concrete
curb and gutter will be installed along the streets within the Glen Addition. Spot curb
and gutter replacement will be completed elsewhere within the project, with structurally
deficient curb being replaced. All streets within the project will be reconstructed to their
current widths to minimize impacts.
Reconstruction of the streets to the City’s standard 7-ton design is proposed to consist of
the following section: 1 ½-inches of bituminous wearing course, 2-inches of bituminous
base course, and 6-inches of reclaimed aggregate base over an acceptable, compacted
th
subgrade. 2-inches of bituminous wearing course are proposed for 207Street, as it is
identified as a minor collector by the City’s Comprehensive Transportation Plan.All
streets within the project will be re-established to include a 6-inch crown, further
Figure 2Appendix A
promoting drainage within the roadways. of illustrates this
proposed roadway section.
2.4.2Storm Sewer
Reconstruction of the streetsprovides the opportunity to improve drainage within the
project areaswith the installation of additional storm sewer facilities. Proposed drainage
improvements within the project include:
th
Installing additional catch basins along Iberia Avenue, 205Street, Hughes
Avenue and Howland Avenue.
Replacing the CMP culvert that currently drains Hughes Avenue with a storm
sewer structure that will connect to the new storm sewer facilities proposed along
th
205Street between Hughes Avenue and Howland Avenue.
Installing a storm sewer manhole structure within the Howland Avenue cul-de-sac
to eliminate the ineffective curb cuts that are currently intended to drain the cul-
de-sac.
Installing a water quality manhole adjacent to Howland Avenue prior to
discharging runoff generated within the project areas to the drainage channel
referred to as South Creek.
Storm sewer improvements are also proposed within the Glenn Addition and along
thth
Lower 208Street and 208Street.
Glenn Addition
Installing concrete curb andgutter within the Glenn Addition, where bituminous curb
currently exists, will provide another means by which to improve drainage within that
neighborhood. Runoff collected within the Glenn Addition flows to existing regional
stormwater basin SC-41-1, asidentified by the Lakeville Water Resources Management
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 6
Plan, dated June 2008. The plan also indicates that the existing regional basin is
adequately sized to accommodate the entire drainage area contributing to runoff collected
within the Glenn Addition.
th
Within the project area, 207Street is identified as a State Aid Street on the City’s
Municipal State Aid System (MSAS). No State Aid Funds are proposed to be used with
th
the reconstruction of 207Street, and therefore, State Aid Standards for stormsewer
design do not apply.
thth
Lower 208Street and 208Street
thth
Storm sewer improvements have been identified for Lower 208Street and 208Street.
th
Two catch basins located at the low point of Lower 208Street currently drain more than
24 acres within that neighborhood. These catch basins discharge to the drainage channel
th
north of Lower 208Street, referred to as South Creek. The existing 15-inch storm
sewer pipe discharges to the channel at an elevation approximately 4-feet below the 100-
year high water elevation for the channel, as identified by FEMA’s Flood Insurance Rate
Map for the area. Stormwater collects within the street during larger storm events as the
water elevation within the channel rises and backs up into the storm sewer pipe. The
observed emergency overflow (EOF) for the low point of the road is higher than the
elevation of the garage and low floor openings for the properties located at 8330 and
th
8340 Lower 208Street, causing water to back up into the garages and lower levelsof
these homes.
To alleviate street flooding issues in this area it is necessary to discharge storm water to
an area of the channel with a high water level (HWL) that is lower than the HWL at the
existing storm sewer discharge point. By directing all of the stormwater collected along
thth
Lower 208Street and 208Street to the easterly cul-de-sac, and installing storm sewer
th
along the shared lot line between 8200 and 8241 208Street, discharge can be made into
an area of the channel where the HWL is approximately 2 ½-feet lower. Ten-foot
drainage and utility easements (DUE) were platted on both sides of the aforementioned
lot line, as this area currently serves as an emergency overflow for the cul-de-sac. The
proposed storm sewer layout will allow a storm water quality manhole to be installed
within the paved cul-de-sac area, making it easily accessible for Public Works staff to
clean and maintain. Similarly, City staff will be able to access the storm sewer pipe
th
discharging to the channel via 210Street right of way and City-owned property as an
alternative to using drainage and utility easements to gain access the pipe.
thth
Final design of the storm sewer improvements along Lower 208Street and 208Street
should include modeling the hydrology for the area to determine if further increasing the
size of the pipe discharging to the channel and/or revising the EOF at the low point for
th
Lower 208Street could provide further protection from flooding during large storm
th
events for the residents locatedat 8330 and 8340 Lower 208Street.
Water quality manholes are proposed for the new storm sewer along Howland Avenue
th
and 208Street, prior to discharging runoff generated within the project areas to the
drainage channel referred to as South Creek.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 7
Figure 3, Figure 4 Figure 5
Proposed storm sewer improvements are shown on and in
Appendix A
.
2.4.3Water and Sanitary Sewer Improvements
In the fall of 2010, the City’s Public Works Department televised the sanitary sewer,
completed a water main leak detection test and evaluated all of the water main valves
within the project. Seventeen (17) sanitary sewer manholes were identified as
structurally deficient and will be reconstructed as a part of this project. The costs
associated with sanitary sewer manhole reconstruction will be funded entirely using City
Trunk Sanitary Sewer funds. No water main pipe, valves or hydrants are proposed to be
repaired/replaced with this project.
2.4.4Street Sign Replacement
All existing street signs within the project will be replaced with new street signs that meet
the Federal Highway Administration’s (FHWA) requirements for retroreflectivity.
2.4.5Mailbox Replacement
Those mailboxes disturbed by the installation of newconcrete curb and gutter or storm
sewer facilities will be replaced as a part of this project. Moving forward, it will be the
City’s policy to replace all mailboxes within street improvement project areas where curb
is being removed and replaced. The City is in the process of updating its Standard
Details to include a new specification for all mailboxes installed within a City of
Lakeville right of way. This detail will also meet United States Postal Service (USPS)
requirements. At the time of this report, only those mailboxes within the Glenn Addition
are proposed to be replaced with the project.
2.4.6Permits/Approvals
An NPDES permit for construction activity will be required as more than 1 acre will be
disturbed with the project.
ARight of Releasefrom Progressive Railway is required for:
th
The surface improvement work identified along 207Street abutting the railroad
rightofway, and
The storm sewer work leading to regional stormwater basin SC-41-1, which is
located within the railroad right of way.
th
At this time, street improvements for 207Street are only proposed within City right of
way. Progressive Railway has indicated that it may be interested in extending the street
improvements to the railway crossing and that cost sharing opportunities with
Progressive Railway exist for work within the railroad right of way. The potential for
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 8
street improvements within the railroad right of way and cost sharing opportunities will
be reviewed by Progressive Railway once preliminary plans havebeen prepared.
A Dakota County Work in Right of Way permit is required for:
Work within the Dodd Boulevard (CSAH 9) right of way adjacent to the Glenn
Addition
Work within the Kenwood Trail (CSAH 50) right of way adjacent to Iberia
Avenue and Hunter Court
2.4.7Construction Access
The contractor will be responsible for providing access to all properties throughout the
project.Adequately signed detours will be identified to direct traffic around the
construction zones and notify users of the increased truck and construction activity.
2.4.8Public Involvement
A public informational meeting for the proposed project was conducted October 28,
2010. Preliminary information was presented to attendees regarding the proposed
improvements, costs, funding, schedule, and impacts associated with the project.
Comment cards were made available to attendees at both meetings. One comment card
was received at City Hall after the October 28 meeting. Summaries of the
correspondence received and questions and answers provided at the informational
Appendix E.
meetings are included in
2.5Future Improvements and Additional Considerations
2.5.1Street Lighting within the Glenn Addition
At the October 28, 2010Neighborhood Meeting, a resident inquired about the possibility
of installing additional street lighting within the Glenn Addition as a part of this street
improvement project. Currently, only the street intersections are lighted by mast-arm-
style lights atop wooden utility poles.
The installation of new street lighting within a neighborhood is an additional special
benefit, and the cost to be assessed shall be 100% of the cost of installing the new
streetlight facilities. A thorough review of the costs associated with the installation of
additional streetlights and a survey of resident opinion can be added to the scope of this
project, as was done with the 2007 Street Improvement Project within the Dakota Heights
neighborhood, at the direction of the City Council.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 9
3.FINANCING
3.1Opinion of Cost
Appendix B
Detailed opinions of cost for the various project areas can be found in of this report.
The opinions of cost incorporate estimated 2011 construction costs and include a 10%
contingency factor. Administrative costs are projected at 28% of the construction cost and
include engineering, legal, financing, and administrative costs.
Table 2
below provides a summary of the opinions of probable cost for the 2011 Street
Improvement Project.
Table 2 –2011 Street Improvement Project
Summary of Cost
Total
Schedule A –Surface Improvements$1,693,000
Schedule B –StormSewer Improvements$961,000
Schedule C -Glenn Addition Curb and Gutter$148,000
Schedule D –Sanitary Sewer Improvements$18,000
TOTAL$2,820,000
3.2Funding
Financing for the 2011 Street Improvement Project will come from City Funds and Special
Assessments.
The sanitary sewer repairs are proposed to be financed by the City’s Operating Fund. Special
Assessments to benefiting properties are proposed to fund 40% of the surface and storm sewer
improvements identified for the project, with the remaining 60% funded using City funds. Those
th
properties located within the Glenn Addition where bituminous curb currently exists (205
th
Street, Idalia Avenue, Iceland Avenue and 207Street) will receive the additional special benefit
of new concrete curb and gutter. As such, 100% of the costs associated with the new concrete
curb and gutter within the Glenn Addition shall be assessed. Assessments for this project were
calculated on a per parcel (unit) basis as identified in the City’s Assessment Policy.
The funding level anticipated through the levy of Special Assessments to benefitting property
$1,210,000
owners for street improvements is with the following proposedassessments:
$6,655.59
Single Family Unit Assessment Rate –Glenn Addition..........................per unit
$4,274.30
Single Family Unit Assessment Rate –All other project areas...............per unit
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 10
Appendix C
The proposed assessment roll is included in of this report, along with an Assessment
Map ID highlighting the benefitting properties and the assessment calculations for benefitting
property owners.
Table 3–2011 Street Improvement Project
Funding Summary
Funding SourceAmount
Streetand Storm Sewer Assessments$1,210,000
City Operating Funds$18,000
City Park Assessments (James Jensen and Terrace Parks)$8,500
City CIP Funds$1,583,500
SUBTOTAL = $2,820,000
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 11
4.PROJECT SCHEDULE
The proposed project schedule for the 2011StreetImprovement Project is as follows:
Neighborhood Open House Held ..............................................................October 28, 2010
Review Preliminary Feasibility Report..................................................December 16, 2010
Accept Feasibility Report/Set Public Hearing.......................................December 20, 2010
Public Hearing/Order Project.....................................................................January 18, 2011
Approve Plans and Specifications/Authorize Ad for Bids............................March 7, 2011
Open Bids/Compute Assessments...............................................................March 30, 2011
Declare Costs/Set Assessment Hearing...........................................................April 4, 2011
Assessment Hearing.......................................................................................April 18, 2011
Award Construction Contract.........................................................................May 16, 2011
Begin Construction*.......................................................................................May 23, 2011
Certify Assessments to County....................................................................November 2011
Final Completion….....................................................................................November 2011
*Schedule assumes any necessary private utility work is completed prior to start of
construction.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 12
5.FEASIBILITY AND RECOMMENDATION
The 2011 Street Improvement Project includes roadway reclamation, reconstruction, and storm
ththth
sewer improvements along 205Street, Idalia Avenue, Iceland Avenue, 207Street, 207Court,
th
Iberia Avenue, Hughes Avenue, Howland Avenue, Hunter Court, Upper 206Street, Lower
thth
208Street, and 208Street. New concrete curb and gutter will be installed along all streets
within the Glenn Addition where bituminous curb currently exists. Spot curb and gutter
replacements will be made elsewhere within the project.Structurally deficient sanitary sewer
manholes identified by the City’s Public Works Department will also be replaced as a part of this
project.
The total estimated cost for the 2011 Street Improvement Project including roadway and storm
$2,820,000
sewer improvements is .Proposed funding for the project is provided through a
combination of Special Assessments and City funds.
This project is feasible, necessary, and cost-effective from an engineering standpoint. It is
recommended to proceed with the improvements as outlined in this report.
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Page 13
APPENDIX A
Figure 1: Location Map
Figure 2: Typical Section –Local Streets
th
Figure 3: Proposed Street and Storm Sewer Improvements –205Street,
thth
Idalia Avenue, Iceland Avenue, 207Street, 207Court
Figure 4: Proposed Street and Storm Sewer Improvements –Iberia Avenue,
th
205Street, Hughes Avenue, Howland Avenue, Hunter Court
th
Figure 5: Proposed Street and Storm Sewer Improvements –Upper 206Street,
thth
Lower 208Street, 208Street
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Legend
Project Location
±
0400800
Feet
2011 CIP Street Reconstruction
WSB NO. 01715-72
Project Location Map
Figure
Lakeville, Minnesota
1
File: K:\01715-72\GIS\Maps\Figure 1 - Location Map.mxd, Dec 08, 2010 9:43:06 AM
Legend
Proposed Storm Sewer
"
Existing Storm Sewer
"
Existing Sanitary Sewer
"
Existing Water Main
Proposed Street Improvement
±
0100200
Feet
2011 CIP Street Reconstruction
WSB NO. 01715-72
Proposed Street and
Figure
Storm Sewer Improvements
3
Lakeville, Minnesota
File: K:\01715-72\GIS\Maps\Figure 3.mxd, Dec 08, 2010 2:59:54 PM
Legend
Proposed Storm Sewer
"
Existing Storm Sewer
"
Existing Sanitary Sewer
"
Existing Water Main
Proposed Street Improvement
±
0100200
Feet
2011 CIP Street Reconstruction
WSB NO. 01715-72
Proposed Street and
Figure
Storm Sewer Improvements
4
Lakeville, Minnesota
File: K:\01715-72\GIS\Maps\Figure 4.mxd, Dec 08, 2010 3:02:58 PM
Legend
Proposed Storm Sewer
"
Existing Storm Sewer
"
Existing Sanitary Sewer
"
Existing Water Main
Proposed Street Improvement
±
0150300
Feet
2011 CIP Street Reconstruction
WSB NO. 01715-72
Proposed Street and
Figure
Storm Sewer Improvements
5
Lakeville, Minnesota
File: K:\01715-72\GIS\Maps\Figure 5.mxd, Dec 08, 2010 3:03:29 PM
APPENDIX B
2011 Street Improvement Project Opinion of Probable Cost
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
Opinion of Probable Cost
WSB Project:Design By:
2011 Street Improvement ProjectMRH
Project Location:Checked By:
City of Lakeville
City Project No.:
11-02
WSB Project No:Date:
1715-7212/16/2010
MN/DOTEstimated
Estimated
Item No.SpecificationDescriptionUnitTotalEstimated Total Cost
Unit Price
No.Quantity
A. SURFACE IMPROVEMENTS
12021.501MOBILIZATION LUMP SUM1$43,800.00$43,362.00
22101.511CLEARING ACRE1.00$2,500.00$2,500.00
32104.501REMOVE CURB AND GUTTERLIN FT7431$5.00$37,155.00
42104.503REMOVE CONCRETE WALKSQ FT655$0.75$491.25
52104.505REMOVE CONCRETE DRIVEWAY PAVEMENTSQ YD125$7.00$875.00
62104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENTSQ YD291$2.00$582.00
72104.509REMOVE SIGNEACH32$50.00$1,600.00
82104.511SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT590$4.50$2,655.00
92104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT1865$2.50$4,662.50
102104.513MILL BITUMINOUS STEP JOINTLIN FT935$3.00$2,805.00
112105.501COMMON EXCAVATIONCU YD10747$9.50$102,096.50
122105.507SUBGRADE EXCAVATIONCU YD538$12.00$6,456.00
132105.522SELECT GRANULAR BORROW (CV)CU YD2079$11.00$22,869.00
142112.501SUBGRADE PREPARATIONROAD STA138$150.00$20,700.00
152118.604AGGREGATE SURFACING, CLASS 2 (4.0" THICK) SQ YD27$30.00$810.00
162123.610STREET SWEEPER (WITH PICKUP BROOM)HOUR9$115.00$1,035.00
172130.501WATERM GALLONS88$30.00$2,640.00
182211.501AGGREGATE BASE CLASS 5 TON3248$14.00$45,472.00
192331.604BITUMINOUS PAVEMENT RECLAMATIONSQ YD42654$2.00$85,308.00
202331.607REMOVE EXCESS RECLAIMED MATERIAL (LV)CU YD500$5.00$2,500.00
212357.502BITUMINOUS MATERIAL FOR TACK COATGALLON15392$2.50$38,480.00
222360.501 TYPE 1 1/2" MVWE 35035B WEAR COURSETON4272$60.00$256,320.00
232360.502 TYPE 2" LVNW 35030B BASE COURSETON5512$55.00$303,160.00
242360.503 TYPE MVWE45035B WEARING COURSE(DRIVEWAYS)SQ YD291$25.00$7,275.00
252504.602IRRIGATION SYSTEM REPAIRLUMP SUM3$500.00$1,500.00
262504.602ADJUST VALVE BOXEACH25$350.00$8,750.00
272506.522ADJUST FRAME AND RING CASTING (SANITARY)EACH44$300.00$13,200.00
282521.5014" CONCRETE WALKSQ FT655$6.00$3,930.00
292531.501CONCRETE CURB & GUTTER DESIGN B612LIN FT113$13.00$1,469.00
302531.501CONCRETE CURB & GUTTER DESIGN B618LIN FT4873$13.00$63,349.00
312531.603CONCRETE CURB & GUTTER SURMOUNTABLELIN FT822$17.00$13,974.00
322531.5076" CONCRETE DRIVEWAY PAVEMENTSQ YD125$40.00$5,000.00
332531.602PEDESTRIAN CURB RAMPEACH3$300.00$900.00
342531.603CONCRETE RIBBON CURBLIN FT23$11.00$253.00
352531.618TRUNCATED DOMESSQ FT24$35.00$840.00
362540.602MAIL BOX EACH62$175.00$10,850.00
372563.601TRAFFIC CONTROLLUMP SUM3$15,000.00$45,000.00
382564.602F & I SIGN PANEL LS1$4,548.00$4,548.00
392571.502DECIDUOUS TREE 2.5" CAL B&BTREE2$250.00$500.00
402573.502SILT FENCE, TYPE HEAVY DUTYLIN FT1500$2.50$3,750.00
412573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH3$500.00$1,500.00
422575.505SODDING TYPE LAWN (INCL TOPSOIL & FERT)SQ YD9300$3.50$32,550.00
Subtotal Schedule A - Surface Improvements$1,203,672.25
+ 10% Contingencies$120,367.23
Subtotal$1,324,039.48
+ 28% Indirect Cost$370,731.05
Schedule A Total - Surface Improvements$1,694,770.53
B. STORM SEWER IMPROVEMENTS
422104.501REMOVE SEWER PIPE (STORM)LIN FT2012$6.50$13,078.00
432104.509REMOVE MANHOLE OR CATCH BASINEACH16$200.00$3,200.00
440214.523SALVAGE CASTING (STORM)EACH8$75.00$600.00
452501.51524" RC PIPE APRON WITH TRASH GUARD AND SHEET PILINGEACH2$2,000.00$4,000.00
462501.51536" RC PIPE APRON WITH TRASH GUARD AND SHEET PILINGEACH2$3,000.00$6,000.00
472502.5414" PERF PVC PIPE DRAINLIN FT228$15.00$3,420.00
482503.52136" SPAN RC PIPE-ARCH SEWER CLASS IIALIN FT294$75.00$22,050.00
492503.52144" SPAN RC PIPE-ARCH SEWER CLASS IIALIN FT327$125.00$40,875.00
502503.54112" RC PIPE SEWER DESIGN 3006 CL VLIN FT515$27.00$13,905.00
512503.54115" RC PIPE SEWER DESIGN 3006 CL VLIN FT1586$31.00$49,166.00
522503.54118" RC PIPE SEWER DESIGN 3006 CL IIILIN FT1487$33.00$49,071.00
532503.54121" RC PIPE SEWER DESIGN 3006 CL IIILIN FT1626$37.00$60,162.00
542503.54124" RC PIPE SEWER DESIGN 3006 CL IIILIN FT1273$42.00$53,466.00
552503.54130" RC PIPE SEWER DESIGN 3006 CL IIILIN FT1149$50.00$57,450.00
562503.54133" RC PIPE SEWER DESIGN 3006 CL IIILIN FT285$60.00$17,100.00
572503.54136" RC PIPE SEWER DESIGN 3006 CL IIILIN FT1259$70.00$88,130.00
582503.54148" STORMWATER TREATMENT SYSTEMEACH1$15,000.00$15,000.00
592503.54172" STORMWATER TREATMENT SYSTEMEACH1$40,000.00$40,000.00
602503.602CONNNECT TO EXISTING STORM SEWEREACH1$600.00$600.00
612506.501CONST DRAINAGE STRUCTURE DESIGN SPECIAL 1EACH61$1,500.00$91,500.00
622506.502CONSTRUCT DRAINAGE STRUCTURE DESIGN 60" MHEACH15$2,500.00$37,500.00
632506.522ADJUST FRAME AND RING CASTING (STORM)EACH20$300.00$6,000.00
642573.530STORM DRAIN INLET PROTECTIONEACH80$125.00$10,000.00
Subtotal Schedule B - Storm Sewer Improvements$682,273.00
+ 10% Contingencies$68,227.30
Subtotal$750,500.30
+ 28% Indirect Cost$210,140.08
Schedule B Total - Storm Sewer Improvements$960,640.38
C. GLENN ADDITION CURB AND GUTTER IMPROVEMENTS
652531.501CONCRETE CURB & GUTTER DESIGN B618LIN FT8066$13.00104,858.00$
Subtotal Schedule C - Glenn Addition Curb and Gutter Improvements104,858.00$
+ 10% Contingencies$10,485.80
Subtotal$115,343.80
+ 28% Indirect Cost$32,296.26
Schedule C Total -Glenn Addition Curb and Gutter Improvements$147,640.06
D. SANITARY SEWER IMPROVEMENTS IMPROVEMENTS
662506.502RECONSTRUCT SANITARY MANHOLEEACH17$750.00$12,750.00
Subtotal Schedule D - Sanitary Sewer Improvements$12,750.00
+ 10% Contingencies$1,275.00
Subtotal$14,025.00
+ 28% Indirect Cost$3,927.00
Schedule D Total -Sanitary Sewer Improvements$17,952.00
Grand Total - 2011 Street Improvement Project$2,821,002.98
APPENDIX C
Assessment Map ID
Assessment Roll
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
File: K:\01715-66\GIS\Maps\Segments_CIP2011_11x17_Aerial.mxd, Oct 04, 2010 10:27:25 AM
APPENDIX D
2010 Geotechnical Report –Log of Test Borings
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
APPENDIX E
Neighborhood Informational Meeting Minutes –October 28, 2010
Public Comment Summary
Feasibility Report
2011 Street Improvement Project
City of Lakeville, MN
WSB Project No. 1715-72
EngineeringPlanningEnvironmentalConstruction 701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763-541-4800
Fax: 763-541-1700
Memorandum
To: Steve Mielke, City Administrator
Chris Petree, Operations and Maintenance Director
Troy Grossman, Street Superintendent
Keith Nelson, City Engineer
Zach Johnson, Assistant City Engineer
From: Monica Heil, Project Engineer
Date: October 29, 2010
Re: City Project No.11-02
WSB Project No. 1715-72
A Neighborhood Meeting was held on Thursday, October 28, 2010 to discuss the proposed 2011
Street Improvement Project, City Project #11-02. Approximately 35-40 residents attended the
meeting held at the Lakeville Senior Center to discuss the proposed improvements. The
following Staff and WSB & Associates, Inc. representatives were in attendance:
Chris Petree, City of Lakeville, Operations and Maintenance Director
Troy Grossman, City of Lakeville, Street Superintendent
Zach Johnson, City of Lakeville, Assistant City Engineer
Jay Kennedy, WSB & Associates, Inc.
Morgan Dawley, WSB & Associates, Inc.
Monica Heil, WSB & Associates, Inc.
The following is a summary from the Question and Answer portion of the presentation:
Question #1 (Q1):
How will the assessments be paid?
Answer #1 (A1):
The City is proposing a 20-year amortization schedule at approximately 4.0%.
Q2:
Why isn’t tax revenue paying for the reconstruction of these public streets? Why can’t
revenue from the Lakeville Liquor Stores be used to pay for this project?
A2:
Approximately 60% of the project costs will be paid for by the City using funds
generated by property taxes. Approximately 40% of the project will be paid by
assessments for those residents living in the neighborhoods where the reconstruction will
take place and the greatest benefit from the project will be received. The City of
Lakeville policymakers have determined that profits generated by the Lakeville Liquors
Stores will be used for other Capital Improvement Projects.
St. Cloud
Minneapolis
Equal Opportunity Employer
K:\01715-72\Admin\Docs\10 28 10 Neighborhood Meeting Minutes.doc.docx
Lakeville 2011 Street Improvement Project Neighborhood Meeting Minutes
October 29, 2010
Page 2
Q3:
How will I get to my home during construction of there is only one entrance to the
neighborhood? (This question was posed by a resident living along Hunter Court)
A3:
The contractor will be required to maintain access to properties during construction.
Q4:
Will this street re-construction project impact the City’s Downtown Redevelopment
Plan?
A4:
No, this project will not impact the Downtown Redevelopment Plans.
Q5:
Are townhomes assessed differently?
A4:
Yes. Per the City’s assessment policy, townhomes and duplexes are assessed 50% of the
single family unit rate. Commercial/Industrial uses are assessed 150% of the single
family unit rate, and apartments are assessed 25% of the single family unit rate per
apartment unit.
Q6:
I have a new driveway in an area receiving all new curb…..what is going to happen to my
driveway?
A6:
It may be necessary to remove a portion of your driveway within the right-of-way in
order to accommodate the new curb and gutter. In this case, driveways will be replaced
in-kind, i.e. concrete driveways will be replaced with concrete, bituminous driveways
will be replaced with bituminous.
Q7:
The watermain in my street was installed within the development 40-years ago…..the
City is not going to replace this watermain with the project while the street is dug up? Is
the City proposing that these utilities are going to last until the next time the road is
reconstructed 40-years from now? When the City reconstructed the downtown area in
the mid-1990’s, they replaced all the utilities. (This question was posed by a resident
th
living on the corner of 205 Street and Howland Avenue)
A7:
The City’s Utility Department is in the process of inspecting all of the trunk facilities
within the project. Televising of the sanitary sewer was just completed, and they are in
the process of completing leak detection on the fire hydrants. If the project moves
forward, the extent of the repairs necessary will be outlined in the feasibility report. Yes,
the utilities in the downtown area were replaced when those roads were reconstructed in
the mid-1990’s, but those utilities were originally installed in the 1920’s and were 70+
years old at the time of their replacement. The utilities in your neighborhood are
approximately 40-year old, and were constructed with materials and workmanship
superior to those available in the 1920’s.Preliminary results from the televising tapes
and utility inspection indicate that trunk facilities are in good condition. Should the
existing utilities require repair work prior to the next major street reconstruction project
within these neighborhoods, in-situ repair techniques, such as slip lining, now exist which
allow for repairs to be made without open cutting the road.
Q8:
Will there be any water quality improvements like raingardens or ponds with all of the
storm sewer improvements being added?
th
A8:
The existing stormwater basin located south of 207 Street will be evaluated to determine
if improvements will be required to accommodate the additional runoff that will flow
th
through the pond with the addition of new storm sewer along 205 Street, Idalia Avenue,
th
Iceland Avenue and 207 Street. Water quality manholes have preliminarily been
identified for areas elsewhere with the project.
K:\01715-72\Admin\Docs\10 28 10 Neighborhood Meeting Minutes.doc.docx
Lakeville 2011 Street Improvement Project Neighborhood Meeting Minutes
October 29, 2010
Page 3
Q9:
Are these roads the oldest in the City? Why are some people being assessed and not
others?
A9:
These streets are not the oldest in the City, but are among those roads in the poorest
condition as identified in the City’s Pavement Management Plan. Those benefiting
property owners located within the project areas will be assessed. We can discuss after
the meeting if there is a question regarding assessments for any particular property
located within the project (To our knowledge, this property owner did not pursue this line
of questioning after the meeting with any City or WSB Staff).
Q10:
What are the existing/proposed load limits for the streets?
A10:
Residential streets are built to a 7-ton design.
Q11:
What are the major factors leading to the deterioration of our streets?
A11:
Poor drainage is likely the biggest factor. Water that is not draining from the pavement is
finding its way into the street subgrade causing a great deal of damage during freeze-thaw
cycles.
Q12:
What effect does heavy truck traffic have on our roads? We have 5 different waste
haulers that pick up garbage in our neighborhood with 20-ton trucks.
A12:
Road restrictions are in place every spring limiting truck traffic along these streets to 5-
ton/axel. However, school buses, emergency vehicles, and to a certain extent, waste
haulers, are exempt from these restrictions.
Q13:
What about the frequency of waste hauling vehicles in our neighborhoods? Is there
anything that can be done?
A13:
It is difficult to regulate waste haulers, and this issue has been discussed by the City’s
policy makers multiple times over the years. Ultimately, the decision has been made by
the City’s policy makers to allow free enterprise in the waste hauling business to continue
and to allow multiple waste haulers to continue to serve the area. However, your
concerns regarding waste haulers and the effect their vehicles have on your streets will be
included in the comments presented to the City Council regarding this meeting.
Q14:
Can assessments be paid early without interest?
A14:
Yes.
Q15:
Can assessments be deferred?
A15:
Yes. There is a senior citizen deferment policy for those over 65-years of age.
Additional questions regarding deferments, such as those for hardships, will need to be
addressed by the City’s Finance Director.
Q16:
When will streets be opened back up to traffic? Will construction take place all summer?
A16:
The contractor will be required to maintain access to all properties during the project.
The construction will likely be phased, with the contractor working on different streets at
different times throughout the construction season. There will be periods of time where
there will be minor delays and inconveniences during construction, but access will be
maintained.
K:\01715-72\Admin\Docs\10 28 10 Neighborhood Meeting Minutes.doc.docx
Lakeville 2011 Street Improvement Project Neighborhood Meeting Minutes
October 29, 2010
Page 4
Q17:
Will any grading be done with the project?
A17:
The extent of the work required hasn’t been determined. If the project moves forward,
and grading issues will be addressed in order to improve drainage in the area.
Q18:
Can street lights be added to the neighborhood with the project? (This question was posed
by a resident living in the Glen Addition).
A18:
The possibility can be investigated if the neighborhood residents are interested.
Q19:
Is storm sewer being assessed?
A19:
Yes. The City will be paying for 60% of the storm sewer costs from funds generated by
property taxes, and assessments paying for the other 40%.
Q20:
Isn’t the lack of storm sewer in the area the result of negligence in the design of the
streets? Why am I paying for storm sewer if the street wasn’t designed to drain?
A20:
The streets and storm sewer systems were designed to drain, and the deterioration of the
pavement surface has lead to some drainage issues. Storm Sewer design standards are
much different today that they were 40-years ago, and so additional storm sewer is being
proposed to meet today’s design standards.
Q21:
What type of curb will be installed where bituminous curb currently exists (The Glen
Addition)?
A21:
B618
Q22:
Are corner lots being assessed twice for both of the streets?
A22:
No. Assessments are calculated on a per unit rate, not on street frontage.
Q23:
Are we required to pay off the assessments before we sell our house?
A23:
The City does not require this, but the mortgage lender might.
Q24:
If new streetlights were installed, how would they be paid for?
A24:
They would be a separate special assessment.
Q25:
Can entire driveways be replaced as a part of the project?
A25:
Not as a part of the City Project. However, property owners can sometimes reach a deal
with the contractor working on the City Project to do the private driveway work.
Q26:
Will mailboxes be impacted with all the new curb and gutter going in my neighborhood?
(This question was posed by a resident of the Glen Addition)
A26:
Yes, as a part of the project, mailboxes are going to be removed and replaced with
mailboxes meeting City Standards. During construction, temporary mailboxes will be
installed.
Q27:
Will bank-owned properties be assessed?
A27:
Yes.
K:\01715-72\Admin\Docs\10 28 10 Neighborhood Meeting Minutes.doc.docx
Lakeville 2011 Street Improvement Project Neighborhood Meeting Minutes
October 29, 2010
Page 5
Q28:
Are lots assessed by the unit or by the front foot?
A28:
Lots are assessed on a per unit basis.
Q29:
I don’t currently have streetlights in my neighborhood, but I still pay the streetlight
operating fee with my utility bill?
A29:
City Staff will look into this.
Q30:
The last question of the night was not a question but a comment, “Bill the assessments
and build the new streets.”
K:\01715-72\Admin\Docs\10 28 10 Neighborhood Meeting Minutes.doc.docx