CITY OF LAKEVILLE
RESOLUTION
DATE: ; April 16, 2001 RESOLUTION NO.: 01-53
MOTION BY Luick SECONDED BY: Rieb
Resolution Approving Change Orders to Contracts for
City Improvement Project #00-18,
City Hall Expansion/Renovation
.NOW THEREFORE BF IT RESOLVED, that the City Council hereby approves the
following Change Orders to contracts for Project #00-18, City HaII Expansion/Renovation:
Description Contractor Original Previous Proposed Revised
Contract Change Change Contract
Order Order
Structural Steel Mid County Fabricating $30,716.00 214.00 $692.25 $31,408.25
Supply
Structural Steel AME Construction 8,500.00 720.00 9,220.00
Erection
Brick and Pre-cast CCS Concrete & Masonry 46,750.00 1,300.00 48,050.00
Installation (Bid Package 8C)
• Interior Block. CCS Concrete & Masonry 8,135.00 (225.00} 7,910.00.
Walls (Bid Package 8D}
Metal Framing/ Friedges Drywall 97,683.00 (13.00) 97,670.00
Drywall
Aluminum Empirehouse 27,767.00 1,797.00 29,564.00
Entrances
Window Blinds Blinds Plus 1,782.00 (150.00) 1,632.00
.Electrical CommTech 120,362.00 (362.00) 3,951.00 123,951.00
BE IT FURTHER RESOLVED, That the Building Fund is hereby amended as
follows:
Adapted ~IIStP(~ Amended
City Hall Project
Construction projects 1,001,858 35,345 1,037,203
CM fee 31,923. 31,923
General conditions 118,870. 118,870
Architect fee/reimb. 92.578 92.578
Subtotal 1,245,229 1,280,574
Generator 91,800 (13,345) 78,455
Fire Station #4 feasibility 22,000 22 000 -
Total 1,359,029 - 1,359,029
Mayor, City Council, City Administrator
City Council Agenda Item -April 16, 2001 Page -7-
APPROVED AND ADOPTED by the City Council of the City Lakeville this 16th day
of April, 2001.
CITY OF LAKEVILLE
Robert D. Johns ,Mayor
AT ST.•
Charlene Friedges, City rk