HomeMy WebLinkAboutItem 06.jDate: 14 July 2011 Item No.
CONTRACT AMENDMENT WITH SEAFORTH ELECTRIC, INC. TO EXTEND THE
CONTRACT FOR THE LIGHTING RETROFIT PROJECT
Proposed Action
Staff recommends adoption of the following motion: Move to approve the contract
amendment with Seaforth Electric, Inc. to extend the contract for the lighting retrofit
project.
Passage of this motion provides an extension of the contract to 31 August 2011 to allow
for final installation of parking lot and exterior lights.
Overview
The Lighting Retrofit Project replaces exterior building and parking lot lights at the
Central Maintenance Facility, Water Treatment Facility, and Fire Station 4. The City
contracted with Seaforth Electric, Inc. on 31 March 2011. Completion of the
installations was planned for 30 June 2011.
During installation, a defect in the manufacturing process for the light fixtures was found
that resulted in damage to the wires connected to the lights. The manufacturer's
representative verified the defect on site and the manufacturer made the determination
that the fixtures be returned to the factory for modification.
Fixtures from each of the facilities were returned to the manufacturer and will be
returned for installation. The process of returning the fixtures to the manufacturer has
increased the time needed for installation.
Staff has reviewed the contract amendment and recommends approval.
Primary Issues to Consider
• The manufacturing defect was outside the control of Seaforth Electric, Inc.
Extending the contract provides adequate time for the modification and installation
of the fixtures.
Supporting Information
• A co
-the proposed contract amendment and manufacturer's letter is attached.
C ristophef Petr-e
Operations and Maintenance Director
Financial Impact: None
Related Documents (CIP, ERP, etc.):
Notes:
Budgeted: Source:
AGREEMENT dated 18 July 2011, by and between the CITY OF LAKEVILLE, a
Minnesota municipal corporation ( "City "), and SEAFORTH ELECTRIC, INC., a Minnesota
corporation (the "Contractor ").
1. EXISTING AGREEMENT. The parties have previously entered into a Contract
for the lighting retrofit project dated 31 March 2011 which is incorporated herein by this reference
shall remain in full force and effect except as specifically modified by this First Amendment.
2. AMENDMENT. The Contract is amended by changing the required completion
date from 30 June 2011 to 31 August 2011.
CITY OF LAKEVILLE
(SEAL)
FIRST AMENDMENT
TO CONTRACT
BY:
AND
Mark Bellows, Mayor
Charlene Friedges, City Clerk
SEAFORTH ELECTRIC, INC.
BY:
Its
Architectural Lighting Design
St. Anthony Office
2920 Anthony Lane
St. Anthony, MN 55418 -3239
Attn: Bob Early
Regard,
Philips Gardco Field Service
www.sitelighting.com
PHILIPS
Philips Gardco lighting
1611 Clovis Barker rd
Philips Gardco/ Field Service
Subject: City of Lakeville SO #308583,309979 Date: 2011 -07 -01
309980 P.O.# 5500920786
In response to the reported manufacturing defect on products listed on P.O. #
5500920786, Philips Gardco has initiated a recall of components with the intention of
reworking product in an expedited manner. Upon internal investigation, it was
discovered that our production team did not secure the LED pig tails according to our
digital manufacturing documentation. The LED pig tails were un- secured in a manner
that allowed contact with the internal support brackets. This led to the wires being
pinched which compromised the dielectric of the LED power wires. This issue has
been corrected in our manufacturing efforts and should not re- occur. Moving forward,
Gardco is taking the following action to resolve this issue.
Philips Gardco management team met on June 28th and recalled all products from
the distributor's warehouse. This is documented on RMA #'s 312950, 312951 and
312976. Products on RMA #'s 312950, 312951 have already been shipped back to
Philips Gardco's location. These were shipped via YRC tracking# 275 - 881943 -4.
The production team has agreed to turn this product around in 48 hours after receipt
of product.
RMA# 312976 is a bit more complex than the two others. These units have been
installed with a temporary field fix. Our plan 01 action for these units will be to take
exactly Y2 of the units down to be sent back to the factory for repairs. As the cartons
have already been discarded, Philips Gardco will ship new cartons directly to
Seaforth electric. Seaforth will be responsible for taking the units down and re-
installing once they are shipped back. Upon receipt of the first batch, Seaforth will be
sending the second batch to the factory for repairs. We have the same 48 hour
commitment from our production team that we have on the above RMA's.
We are very sorry for the inconvenience caused by this manufacturing error. With the
above action plan, we are well on our way to resolving this issue in its entirety. We
thank you for your time and patience to this ongoing matter.